GOLDAIR HANDLING ENGINE PLANT
PREPARATIONS & CONSTRUCTION WORKS OF INDUSTRIAL FLOOR WITH EPOXY PAINTING IN THE AREA OF THE ENGINE PLANT OF GOLDAIR HANDLING AT THESSALONIKI AIRPORT
Supervision – Construction: Stelios Bigdelis, Stratis Xypteras
Construction of rigid reinforced floor, industrial type, surface hardening with the application of a mixture of quartz aggregates, consisting of C20/25 category concrete, small thickness, reinforced with T131 mesh and 18mm polypropylene fibers.
Application of special epoxy two-component dispersion paint, which meets the specifications for its application on freshly concreted floor with excellent results in mechanical stress. The above paint is of Swiss technology, acquires passability in 12h from its application, complete hardening in 5 days and final strength in 14 days.
For the outer part of the floor to protect the final layer, transparent polyurethane paint was applied, to protect from ultraviolet radiation.
Final Stage
Construction Stages
Ready to Discuss Your Project?

Project planning and supervision for all types of building and electromechanical works. Complete construction, reconstruction, and renovation services for residential and commercial spaces, as well as technical projects. Specialized proposals and full coordination of technical works.
© 2026 Northbuild Construction. All rights reserved.